This week, we all worked on solidifying our project idea.
We presented our project pitch on Tuesday and proceeded to work on our Product Requirements Document (PRD) outlining details for our project.
We made milestones for all the weeks in the quarter, assigned roles, and adjusted our MVP a bit to take into account when it was due (which is February 8th,
around a bit more than 2 weeks from now). We also started considering what assets we wanted as we planned our budget for the PRD.
Our PRD milestones are planned optimistically (in hopes that we can potentially reach some stretch goals). But since we are all
new to developing in VR (and some of us are also new to Unity), we're a bit worried that we might fall behind, and we're not too
sure how accurate our time estimates are for our milestones. We're also uncertain on how difficult some of the different tasks might be, so
we may need to end up readjusting roles.